|
On January 26th, 2011
sometime during the day our Granary started on fire and burned to
the ground. It was a total loss. This will be the Diary of the
project from the start to the finished.
Part One of the
project - the removal of the destroyed building
|
|
 |
.JPG) |
|
Here is the
cabin being removed following the fire. |
The top of
the building being removed |
|
|
|
|
Part Two of the project - installing the new
septic system |
|
There were some discoveries to
the project that we were not expecting. The foundation and the
septic system did not meet current codes so these two portions of
the project were going to have to be replaced prior to rebuilding
the new cabin. In
order to prepare for the septic system installation we needed to
have over 30 tree removed so that we would have a place to set the
tanks and to remove the old system.
Here are pictures of the new
septic system that was installed. The design of the septic system
showed us that the sit soils were going to require an special
system.
|
|
 |
 |
|
Clearing out more than 30
trees (lone pine was the edge of tree line) |
Setting the
first of two tanks |
|
|
|
|
 |
 |
|
Setting the
pump in tank two
|
Measuring the
pad |
|
|
|
|
 |
 |
|
Rock bed |
Next step is
more top sand, then top soil and seed. |
|
|
|
|
 |
.JPG) |
|
Peeling some
top soil for the mound, leveling the yard |
New system -
it is time to groom the yard and seed |
|
|
|
|
Part Three - Preparing for the foundation of
the new cabin |
|
We removed
trees for the new cabin and septic system install. We have decided
to move the cabin back about 25' to accommodate parking spaces in
front of it. This has been requested by guests that we do this.
|
|
%20-%20Copy.JPG) |
.JPG) |
|
Squaring up the foundation |
Installing the poured wall system |
|
 |
 |
|
Foundation of
the new cabin. Just waiting for the building. |
Poured wall foundation is
very energy efficient and strong. |
|
|
|
|
Part Four -
Installing the Geo Thermal Loops |
|
A big part
of our project is to make the retreat center more energy efficient.
As the cost of heating and cooling rise, so does our expenses here
rise. It is our goal to build the most energy efficient cabin
possible for the comfort of our guests and for to reduce expenses.
|
|
.JPG) |
 |
|
One of our trenches for
the geo thermal loop field. |
Here is 3 of
the 8 loops that we installed. |
|
|
|
|
 |
 |
|
At one point
in this project we had almost 1500 lineal feet of open trenches. |
Yes this is me in the
Track Hoe. I did all the digging on this project. |
|
|
|
|
Part Five -
Installing the heating system |
|
Because of our desire to
provide the best source of heat and because of our desire to remove
all sources of fire danger we are installing an in floor heating
system in the new cabin. We did this in the bath house and the new
"Bunk House" and our guests really love it. When it is all over we
will have 5 buildings heated from the same furnace. |
 |
 |
|
This gives you an idea of
how the tubing is laid out inside of the foundation. As you can see
after this is done, the concrete slab will be ready to pour. |
Here shows the manifold that will be used to regulate
the flow of water in the floor. This system will be a three zone
system. |
|
|
|
|
Part Six - The building is going up |
|
The new cabin is being built using SIP (Structural
Insulated Panels) - With this kind of design we will have superior
strength compared to stick framing, superior energy efficiency
compared to stick framing and will give our guests superior comfort
during their stay here at Lindisfarne. |
.JPG) |
 |
|
The new cabin after day three |
The view from the tower |
 |
 |
|
Waiting for the Siding, Roofing
and Fascia & Soffits |
Cabin is sided waiting
for Shingles |
 |
 |
Metro Steel Shingles will protect it from summer hail
and because of the
hot roof construction will keep it cooler in the summer. |
New driveway back to the cabin. By using the large
boulders we were able to layer the landscaping in the yard. It
turned out beautiful. Now just waiting for Spring when the grass
seed starts to grow. |